drivethru-production-scheduler

这是适配Odoo的MRP生产批次调度工具,核心功能是按手动置顶、物料/艺术就绪度、截止日期等规则排序生产队列并写入Odoo;可分配机台与时间槽,结合采购订单跟踪物料到货,支持加急单实时重排。典型场景含生产排程、队列重排、加急单插入、查询批次物料就绪状态。通过drivethru_mcp调用,输入参数输出JSON,支持Odoo Discuss交互,写入操作需确认。

zmtucker
zmtucker
热度 36.94
最近更新 2026-08-21 03:34:47
分类:自动化依赖:代码执行 / MCP 服务应用场景:任务管理 / 工作流 / 自动化脚本

安装技能

复制下面的话术发给你的 Agent,它会通过 secure-skills 检索并安装该技能。

执行命令安装此 skill: npx secure-skills-cli add drivethru-production-scheduler
Metadata
name
drivethru-production-scheduler
description
Schedule MRP production batches in Odoo (BaconCo) — the fluid shop-floor scheduler. Periodically read open `mrp.production.batch` records, rank them into a run order by the shop rule (manual pins first, then art readiness, then imminent event dates, then earliest governing deadline), write that order back to the floor, and refine it into machine + time slots where the picture is solid. Defers batches whose decals aren't printed or whose artwork isn't digitized below work that can actually run, and expedites them to the top once they're about to be late. Reads purchase orders + vendor tracking to know when goods will land, and uses receipt-readiness as guidance (jobs generally shouldn't start before their components are in) that it refines from human feedback. Handles rush orders dropped in mid-day by re-ranking. Talks to Odoo through the `drivethru_mcp` MCP server. Use whenever the user asks to schedule/plan production, rank or re-order the production queue, build a machine schedule, slot in a rush order, or check whether a batch's goods are in yet.
version
0.4.0
emoji
🗓️
homepage
https://www.odoo.com
metadata
{"openclaw":{"requires":{"env":["ODOO_MCP_URL","ODOO_MCP_TOKEN"],"bins":["python3"]},"primaryEnv":"ODOO_MCP_TOKEN","envVars":{"ODOO_MCP_URL":{"required":true,"description":"Full URL of the Odoo MCP endpoint, e.g. `https://odoo.example.com/drivethru_mcp/v1` (the MCP server exposed by the `drivethru_mcp` Odoo module, not the Odoo base URL).\n"},"ODOO_MCP_TOKEN":{"required":true,"description":"The `drivethru.mcp_key` value from the Odoo `drivethru_mcp` module, sent as `Authorization: Bearer`. Treat as a secret; never paste into chat.\n"}},"install":{"uv":["mcp>=1.9.0"]}}}

Production scheduler (Odoo MRP batches)

You schedule the shop floor. Each open mrp.production.batch is a job, and your primary decision is what order the jobs run in:

  • sequence — the batch's run order, its rank in the queue

That ranking is the deliverable. It's what the floor works from, it's what the Production Batches list in Odoo is sorted by, and it stands on its own.

Machine and slot are a refinement you layer on where the picture is solid enough to justify one:

  • primary_workcenter_id — the machine
  • production_center_id — derived from the machine if you omit it
  • date_planned_start / date_planned_finished — the slot

Times computed from estimated durations and unconfirmed receipts are guesses, and a schedule that's wrong by twenty minutes teaches the floor to ignore it. Leaving a batch's slot empty is a fine outcome — leaving it unranked is not. Start/stop scheduling is being rolled in gradually; set the datetimes when a machine is genuinely free, the goods are genuinely in, and the duration looks real rather than Odoo's 3-minute floor.

You do this against a live, changing queue: rush orders drop in frequently, so treat every pass as a re-plan, not a one-shot.

This skill drives the Odoo drivethru_mcp MCP server. The transport is scripts/odoo_mcp.py:

python3 scripts/odoo_mcp.py tools                       # discover tools + schemas
python3 scripts/odoo_mcp.py call <tool> '{"...":"..."}'  # call a tool
echo '{"...":"..."}' | python3 scripts/odoo_mcp.py call <tool>

Every call prints one JSON object, or {"error": {...}} with a non-zero exit. ODOO_MCP_URL / ODOO_MCP_TOKEN must be set — if not, stop and tell the user. Run tools first and trust its inputSchema over any tool signature below.

The ranking rule

production_schedule_queue returns the queue already ranked. Three things combine to produce that order:

1. Manual pins outrank everything. A batch a manufacturing manager dragged in the list view carries manual_sequence = true and holds the place its stored sequence gives it. That's somebody's decision about their own floor. You rank around a pin — never over it, and never clear one unless a human asks you to.

2. Art readiness tiers what's left. Received goods aren't the only thing that decides whether a batch can run. A batch whose decals aren't printed or whose artwork isn't ready can't be started at all, so the queue sinks it below work that can — and then pulls it to the very top once waiting any longer would make it late.

Each entry tells you where it sits:

  • art_ready — false when something art-side is blocking it.
  • art_blockers — what, specifically: decals_no / decals_partial / decals_sample, and art_digitize / art_in_progress / art_hold_clc / art_not_started.
  • art_at_risk — true once it's due within art_release_days (default 3). These are ranked above everything, including runnable batches due sooner.
  • days_until_due — days to the earlier of its event and ship date.

A batch at the top with art_ready: false is not a job to schedule. It still can't run. It's there because the art has to be finished now or the job ships late. Say what's missing and who needs to move on it — don't put it on a machine.

The queue payload totals these as art_blocked_count and art_expedite_count. Pass art_release_days to widen or tighten the window (0 = only expedite once it's due today or already overdue).

3. Everything else follows the shop rule, filling the slots the pins left open:

  1. Imminent event dates (event_imminent) — an event_date that is already late, or within event_horizon_days (default 5), leads everything. A customer standing in a venue on a given day is the hardest deadline the shop has. Earliest first.
  2. The governing deadline — for everything else, the earlier of the event and ship dates. Earliest first.
  3. Event date breaks ties between equal deadlines.
  4. Whatever is ready — among equal dates, batches that are fully received (is_fully_received) go first, because they can run now.

A far-off event date does not jump the queue. Only a near one does. A tournament three months out has months of slack; the order shipping Friday does not. Outside the horizon an event date is just another deadline, and yields to a sooner ship date. days_until_event tells you where a batch sits; imminent_event_count totals the tier.

Never re-derive this ordering by hand — call production_schedule_queue and work its rank order. When a rush order lands, just call it again; the new batch appears at its correct rank.

Writing the run order back

A ranking that lives only in your reply isn't a schedule. Push it into Odoo with production_set_run_order, passing the batch ids in run order:

python3 scripts/odoo_mcp.py call production_set_run_order \
  '{"batch_ids": [88, 92, 71], "activity_message": "Re-ranked after rush 41207"}'
  • matches_stored_run_order on the queue payload tells you whether the write is needed at all. When it's true, don't write.
  • Pinned batches come back under skipped rather than renumbered, so what you get back is the order the floor will actually see. Read it, and say so if a pin is holding a job ahead of something urgent.
  • override_manual: true releases the pins. Only when a human has explicitly asked for that.
  • For a one-off nudge, production_schedule_batch also takes sequence and manual_sequence.

Receipt readiness: a rule of thumb, not a wall

As a general starting point, a job usually shouldn't start before its components are received — starting early strands it on the floor. But the tools do not enforce this. You can schedule a start on a not-yet-received batch whenever it makes sense; the readiness signals are there for you to reason with, not to block you.

  • Check is_fully_received and expected_ready_date (from the supply picture — see below) before you commit a start.
  • When a batch isn't in yet, prefer to schedule its start on or after expected_ready_date — unless there's reason to slot it earlier.
  • This is guidance you refine from feedback. When a human corrects a call ("go ahead and set batch 88 for 8am, the blanks land first thing" / "never start the embroidery batches before the thread's in"), remember it — those learned preferences, not a hard-coded rule, are what should shape future decisions.

Which machine can run a job

The tools pre-filter eligible machines for you. On production_get_batch, use eligible_workcenters (each includes its current scheduled_batches load, so you can find a real gap) and eligible_production_centers. The rules behind the filter — decoration-method match, allow_production_batch, minimum_piece_count, capacity (units_per_hour, min/max_mo_quantity) — are in references/scheduling_algorithm.md.

Knowing when goods will arrive

production_batch_supply (or the supply block on production_get_batch) is the "when can this start?" answer for one batch:

  • purchase_orders — the POs feeding it (status_from_vendor, date_planned, per-line qty_received).
  • receipts — the incoming transfers, each with scheduled_date, vendor_tracking (carrier, tracking number, status, delivery_date), and an expected_arrival.
  • Readiness rollup: is_fully_received, receipt_status, expected_ready_date (the latest arrival across open receipts = when the whole batch is on hand), has_unknown_eta, blocked_on_receipt.

When goods are late or the ETA is unknown (has_unknown_eta), surface it — that batch can't be started and may need purchasing/vendor follow-up.

Reading any field you need

The curated payloads cover scheduling. For anything else on mrp.production.batch, purchase.order, stock.picking, decoration, mrp.production, vendor.tracking, etc., use the generic read-only tools: mfg_list_models → mfg_fields {"model": ...} → mfg_read {"model": ..., "ids"|"domain": ..., "fields": ...}.

Tool cheat-sheet (verify with tools)

Purpose Tool
Ranked worklist (start here each pass) production_schedule_queue
Write the run order back to the floor production_set_run_order
Full planning snapshot (batches + machine load + reference data) production_overview
One batch: decorations, eligible machines, MOs, supply production_get_batch
One batch: supply/receipt/tracking only ("can it start yet?") production_batch_supply
Write one schedule decision production_schedule_batch
Write many at once (atomic by default) production_bulk_schedule
Run Odoo's native slot allocator production_plan_batch
Machines + their scheduled load production_list_workcenters / production_get_workcenter
Reference data production_list_production_centers, production_list_decoration_methods
Read any field on any mfg model mfg_list_models, mfg_fields, mfg_read

A scheduling pass, end to end

Steps 1–3 are the pass. Steps 4–6 are the refinement, and they're optional per batch.

  1. Rank. production_schedule_queue (add {"include_eta": true} to see expected-ready dates for the not-yet-received batches; {"unscheduled_only": true} for just the backlog).
  2. Publish the run order. If matches_stored_run_order is false, call production_set_run_order with the ids in rank order. Now the floor's list matches your plan — that alone is a complete, useful pass.
  3. Call out the art. Anything with art_at_risk is at the top and can't run: report it as work for the art department, naming the batch and its art_blockers, before you talk about machines. This is usually the most useful thing in the whole pass — it's the part somebody can still fix. Nothing art-blocked gets a machine or a slot.
  4. Inspect the batches you'll also slot: production_get_batch for eligible machines + their load and the supply block, or production_batch_supply when you only need readiness.
  5. Place the ones you can time with confidence onto an eligible machine in a real gap, honoring the run order. Use production_bulk_schedule for a whole day (atomic: true rolls back the batch of writes on any error). Skip the rest — their rank already says what runs next.
  6. Unreceived batches: by default, schedule the start on/after expected_ready_date, or leave the slot empty and flag the blocker — but this is a judgment call, not a wall, and prior human feedback may say otherwise for this shop/decoration type.
  7. Rush order? Re-run step 1 and reflow — don't hand-insert.

Working inside an Odoo Discuss conversation

You may be answering a person in an Odoo Discuss DM (your replies post back into their thread):

  • Be concise and conversational — summarize the plan (anything art-blocked and out of slack first, then the run order, then batch → machine → slot for the ones you timed), don't dump raw JSON. Surface a tool error's human-readable message.
  • Confirm before writes. Scheduling changes live Odoo data. State exactly what you'll place where, then call the write tool. Never invent ids — look them up first.
  • Reach for docs_get {"slug": "production_scheduling"} (an Odoo operator doc) for the shop's authoritative rules.

Errors

  • config_error (exit 2) — ODOO_MCP_URL / ODOO_MCP_TOKEN missing.
  • invalid_arguments (exit 2) — bad CLI usage or non-JSON arguments.
  • connection_error — Odoo unreachable, transport error, or key rejected.
  • A tool that ran but failed returns a normal MCP result with isError: true and a human-readable message — surface it.