Contractor Quote Duel
Three quotes for "the same" roof project are rarely the same project. One bids 1,900 sq ft of shingles and nothing else; one includes gutters and skylight flashing; one is $4k cheaper because tear-off disposal is a change order waiting to happen. Homeowners compare totals — the single most misleading number in the stack — because building a scope matrix by hand across PDFs is tedious. This skill does the comparison mechanics: scope union, gap exposure, unit-price outliers, payment risk, and the clarification emails that turn apples/oranges into a decision.
When to Use
- 2-4 written quotes in hand for the same project, deciding who gets it
- One bid dramatically cheaper — is it efficient or incomplete?
- Deciding what to ask each bidder before signing anything
- Checking a quote's payment structure before handing over a deposit
- Change-order dispute later: was the item in the original scope?
Don't use for: new construction custom builds (different economics — cost-plus vs fixed-price needs a contract review, not a comparison matrix); storm-chaser door-knockers (walk away, don't analyze); anything needing a structural engineer's stamp (get the engineer).
The Method
- Extract quotes to JSON (agent does this from PDFs/photos/text): bidder, total, deposit %, items (name/price/qty), docs promised, licensed/insured flags.
matrix— scope union × bidder grid; every "— MISSING" cell is a scope gap you'd discover as a change order. Plus documentation completeness per trade (roof quotes without ice/water shield specs, kitchens without permit responsibility, HVAC without load calc).pricecheck— unit price = price/qty vs ballpark band per trade.1.6× band high = padding; < 0.5× band low = lowball — the classic change-order bait.
risk— deposit & payment-schedule exposure. Deposit >30%, nothing written, >60% due before completion, uninsured: LOW/MEDIUM/HIGH.letter— scope-gap clarification email per bidder listing exactly what competitors included that they didn't, plus the four questions (payment schedule, timeline, permits, labor warranty).
Q='[{"bidder":"Alpha Roofing","total":9500,"deposit_pct":10,"insured":true,
"items":[{"item":"asphalt roof replacement","price":9500,"qty":1900}],
"docs":["tear-off layers and disposal included"]},
{"bidder":"Beta Exteriors","total":14200,"deposit_pct":50,"insured":false,
"items":[{"item":"asphalt roof replacement","price":11800,"qty":1900},
{"item":"gutter replace","price":1200,"qty":80}],"docs":[]}]'
python3 scripts/quote_duel.py --quotes-json "$Q" matrix
python3 scripts/quote_duel.py --quotes-json "$Q" pricecheck
python3 scripts/quote_duel.py --quotes-json "$Q" risk
python3 scripts/quote_duel.py --quotes-json "$Q" letter --bidder "Alpha Roofing" --project "roof replacement"
Decision Rules (from the outputs)
- Never decide on totals: decide on normalized scope + unit prices.
- A bid missing >30% of the union scope isn't cheaper — it's undefined. Get the gaps priced before comparing.
- Deposit >30% or >60% pre-completion is walk-risk; many US states cap deposits at 10-30% by trade.
- Cheapest bid + LOW unit-price flags = change-order farm. Budget total × 1.25 as the realistic number.
- Insurance/license unverified = stop. Verify before any money moves.
Common Pitfalls
- Comparing totals across different scopes. The matrix exists precisely because totals lie. Every MISSING cell must be priced or excluded in writing before a decision.
- Forgetting qty. Unit-price checks need quantity (sq ft, linear ft, windows). A $9,500 roof bid without area can't be sanity-checked — ask for measurements.
- Trusting allowances. "Allowance $1,500 for fixtures" is not a price. Convert allowances to spec-or-unit-price in the clarification letter.
- Ballpark bands as gospel. Bands are US national order-of-magnitude; regional spread is 2×. Use flags to ask questions, not to accuse.
- Ignoring documentation gaps. The docs checklist per trade is the cheapest dispute insurance: no ice/water shield spec on a roof quote is how you get felt-only under a $12k roof.
- Paying to a point of no leverage. Final payment after punch list, always. A contractor with 100% of the money has zero incentive to return.
- Verbal "yes that's included." If it isn't a line item after the clarification letter, it doesn't exist.
Verification Checklist
- Every scope item in the union appears in the final contract of the winner (line items, not summaries)
- Unit-price outliers resolved in writing (spec'd or re-priced)
- Deposit <=30%, schedule written, final payment after punch list
- License + insurance verified with the state/insurer directly
- Permit responsibility named in the contract
- Change-order rule written: signed + priced before extra work
References
references/trade-scope-checklists.md— what a complete quote must contain per trade (roof/kitchen/bath/HVAC/electrical/structural), allowance traps, contract clauses that survive disputes, and the lowball-bid pattern catalog.