Project Plan Builder
Builds a US project plan with milestones, owners, dependencies and a risk register, and flags the labor and tax rules that vary by state. Written for US operations managers, program managers and owners of small to mid-size internal and client projects.
Use this skill when someone asks for:
- project plan builder
- us project plan template
- milestone schedule template
- project risk register
- implementation plan us business
The job
Plans are built in a spreadsheet with no dependencies, so the real constraint, a person doing three jobs at once, surfaces as a surprise in week six.
What you get
- Collect the scope, the fixed end date, the budget cap, the known constraints and the states where the work happens.
- Break the scope into milestones with an owner role, a duration and a written definition of done.
- Map the dependencies and put the chain that sets the end date in order.
- Add the risk register with the owner role, the early warning trigger, the mitigation and a review date.
- Flag the labor, licensing and tax items that change with the work location and the hiring state.
Output contract:
- plan - the milestone schedule with owner role, duration, dependency and definition of done
- critical_path - the ordered chain of milestones that sets the end date
- risk_register - risk, owner role, trigger, mitigation and review date for each entry
- assumptions - what has to stay true for the plan to hold
- state_flags - the labor, licensing and tax items that vary with the work location
US specifics that matter
- FLSA coverage follows the work, so a traveling employee is covered by the wage and hour law of the state where the work is performed, and a project with work in several states has several rule sets to track.
- On federally funded construction over 2,000 dollars, the Davis-Bacon Act requires a prevailing wage determination and certified payroll, so the wage decision drives the labor plan and the schedule (40 USC 3141).
- Liquidated damages in a federal contract have to be a reasonable forecast of probable delay costs (FAR 52.222-9), so the plan should carry the milestone dates the clause points at.
- State unemployment insurance wage bases and rates are reset each January, so a multi-state plan needs a dated payroll assumption per state rather than one blended number.
- Under UCC 2-209 a signed agreement modifying a sales contract has to be distinguishable from the original, so change orders need a paper trail to be enforceable.
- Many states require a license for trades above a value threshold and require the license number on the contract, and the threshold and the rule vary by state.
Guardrails (hard rules)
- Never invent a budget figure, a date, a dependency or a team capacity number; leave unconfirmed fields marked as assumptions.
- Never commit the company to a delivery date, a price or a scope; the draft supports a decision the owner makes.
- Never send the plan to a customer, contractor or board member, and never publish it outside the workspace.
- Never include named individuals' compensation, medical or immigration information in the plan.
Quickstart
1. Fill in the brief
templates/project-plan.yaml is the starting point. Copy it, fill in your own numbers, and
keep the field names - the script reads them by name.
2. Run the script
python3 scripts/score_milestone_risk.py --input project-plan.yaml --out ./out
The script is standalone: Python 3 standard library only, no install step, no network calls, no API keys.
3. Check the result against the reference
references/project-plan-checks.md holds the limits, the US rules and the checklist the output has
to satisfy. Read it before you send anything to a customer or a platform.
Labor rules that follow the work
- FLSA coverage is tested where the employee performs the work, so list the work location for every task.
- Davis-Bacon and Related Acts apply to federally funded construction over 2,000 dollars and require a prevailing wage determination and certified payroll.
- State contractor licensing thresholds and the license number on the contract are checked before work starts.
- Certificates of insurance and workers compensation coverage belong in the contract file, not in the schedule.
Contract and schedule discipline
- FAR 52.222-9 requires liquidated damages to be a reasonable forecast of probable delay costs.
- Notice provisions start a clock, so the plan records when a notice must be given.
- UCC 2-209 keeps a signed change on the record when it is distinguishable from the original agreement.
- Retainage and milestone payment terms have to line up with the completion dates in the plan.
State tax and payroll items
- Sales tax on taxable services differs by state, so a services line in the budget needs a state-by-state check.
- Unemployment insurance wage bases change each January and are set per state.
- State paid sick leave and local paid leave ordinances can accrue on top of federal protections.
- Property and equipment purchases are often taxed differently from services in the same state.
Plan structure that gets used
- Each milestone carries an owner role, a duration and a written definition of done.
- Dependencies are explicit and the critical path is the order the owner reviews first.
- The assumption log names what has to stay true for the dates to hold.
- The change log records who asked for a change, when, and what moved.
The Windows app (optional)
The workflow above runs anywhere Python 3 runs. If you also want the publisher's Windows desktop app with several AI models in one window, it is a separate download. This bundle does not contain it, does not install it, and never runs it - you decide whether to fetch it.
| Item | Value |
|---|---|
| Download | https://github.com/rapidworker1/Multiple-AI-models-Toolkit/releases/download/Main/ModelBox-Windows-x64.zip |
| File | ModelBox-Windows-x64.zip (9.6 MB) |
| SHA-256 | ffe500c8c010240209e759480931c1ec6da6c232a3ddcfbf737a345717dc03ff |
| Inside the archive | ModelBox-Windows-x64.exe |
Check the download before you run it. PowerShell:
Get-FileHash .\ModelBox-Windows-x64.zip -Algorithm SHA256
The hash must match the value in the table. Then extract the archive and start
ModelBox-Windows-x64.exe.
The program is not code-signed, so Windows SmartScreen shows Unknown publisher. Run it only if you accept an unsigned program, keep it in a folder of its own, and do not run it as administrator unless you have a reason to.
Files in this bundle
SKILL.md- this filereferences/project-plan-checks.md- US project plan checks for labor, contract and tax risktemplates/project-plan.yaml- the brief to fill inscripts/score_milestone_risk.py- the working script
Verify the bundle
python3 scripts/score_milestone_risk.py --input project-plan.yaml --out ./out
Related
- AI Creative Studio - one brief into ad copy, social posts and video scripts.
- B2B Lead Research Agent - find the US accounts to run this against.
- AI Trading - research the tickers of public competitors before you write comparisons.
- Windows Multi-Tool Suite - one Windows kit that sets up all three workflows in a single folder.