Scenario Planning

该 Skill 提供确定性的项目管理 what-if(情景)分析流程:在已有基线计划上选取不超过 3 个高影响变量,定义情景并修改工期/资源/成本模型,重算工期、关键路径、成本与资源利用率,与基线对比后给出决策与缓解建议。用户需先提供完整基线;概率模拟(蒙特卡洛)不在范围内。

pkacker
pkacker
热度 84.93
最近更新 2026-05-11 17:38:29
分类:协作依赖:纯提示词应用场景:任务管理 / 日程安排 / 报告撰写 / 工作流

安装技能

复制下面的话术发给你的 Agent,它会通过 secure-skills 检索并安装该技能。

执行命令安装此 skill: npx secure-skills-cli add scenario-planning
Metadata
name
scenario-planning
description
Perform project management what-if (scenario) analysis to simulate risks, delays, and resource changes. Use when planning schedules, assessing uncertainty, or evaluating project impacts in tools like Excel, MS Project, or Primavera.

What-if Scenario Planning (WISA)

When to Use

Use this skill when:

  • A project plan needs risk simulation before execution
  • The user asks “what if this changes?” in a project context
  • There is uncertainty in schedule, cost, or resources
  • The user is working in Excel, MS Project, or similar tools

Core Objective

Simulate alternate project scenarios by modifying key variables (duration, resources, cost) and evaluate their impact on:

  • Project timeline
  • Critical path
  • Total cost
  • Resource utilization

Execution Steps

Step 1: Establish Baseline Plan

Ensure a complete baseline exists:

  • Tasks with durations
  • Dependencies (network/PERT)
  • Resources assigned
  • Cost estimates

If missing → ask user to define baseline first.


Step 2: Identify Variables

Extract or ask for uncertain variables:

  • Resource availability
  • Task duration variability
  • Budget constraints
  • External risks (delays, logistics, approvals)

Focus only on high-impact variables (max 3 per scenario).


Step 3: Define Scenario

Create a structured scenario:

Format:

  • Scenario Name:
  • Variable Change:
  • Duration/Impact Change:
  • Time Window (if applicable):

Example:

  • Resource A unavailable for 3 days starting Day 10

Step 4: Modify Project Model

If Excel:

  • Adjust input cells (duration/resource %)
  • Use:
    • Scenario Manager
    • Data Tables

If MS Project / Primavera:

  • Duplicate baseline
  • Modify:
    • Task duration
    • Resource allocation
    • Dependencies if needed

Step 5: Simulate Impact

Recalculate project plan and capture:

  • New project duration
  • Critical path changes
  • Cost variation
  • Delayed milestones

Step 6: Compare with Baseline

Create structured comparison:

Metric Baseline Scenario
Duration
Cost
Critical Path

Step 7: Evaluate Acceptability

Decide:

  • Acceptable → proceed with scenario plan
  • Not acceptable → propose mitigation:
    • Add resources
    • Re-sequence tasks
    • Increase buffer

Step 8: Recommend Action

Always provide:

  • Impact summary
  • Decision recommendation
  • Optional mitigation strategies

Output Format

Return results in this structure:

Scenario Summary

  • Scenario:
  • Key Change:

Impact Analysis

  • Duration Change:
  • Cost Impact:
  • Critical Path Impact:

Recommendation

  • Decision:
  • Suggested Actions:

Rules

  • Do NOT simulate without a baseline
  • Limit scenarios to avoid combinatorial explosion
  • Prefer clarity over complexity
  • Always quantify impact (time/cost)
  • If data is missing → ask user before proceeding

Notes

  • This is deterministic scenario analysis (WISA)
  • For probabilistic analysis, suggest Monte Carlo simulation
  • Best used during planning and scheduling phase

Validation

Before finalizing:

  • Ensure dependencies are preserved
  • Check calculations consistency
  • Validate assumptions with user context
  • Confirm outputs are realistic (no negative durations, etc.)