Evt Dvt Pvt Gate Review

核心功能:按EVT/DVT/PVT各阶段退出标准评分,分类处理开放问题( blocker/豁免/延期),分析良率并生成合规的放行/有条件放行/不放行建议。典型场景:启动门评审、决定阶段进出、评估构建结果、阶段前问题分类。需输入阶段类型、构建结果、问题列表等信息,输出结构化评审文档,含评分卡、问题表、良率分析、豁免登记及明确决策。

mohitagw15856
mohitagw15856
热度 10.47
最近更新 2026-07-16 22:39:21
分类:效率依赖:纯提示词应用场景:报告撰写 / 数据处理 / 模板

安装技能

复制下面的话术发给你的 Agent,它会通过 secure-skills 检索并安装该技能。

执行命令安装此 skill: npx secure-skills-cli add evt-dvt-pvt-gate-review
Metadata
name
evt-dvt-pvt-gate-review
description
Run an NPI phase-gate review for EVT, DVT, or PVT — exit criteria per phase, open-issue triage, yield readout, waiver discipline, and a go/no-go call. Use when asked to run a gate review, decide EVT exit or DVT entry, review build results, assess whether to proceed to the next build, or triage open issues before a phase gate. Produces a gate review document with criteria scoring, waiver register, yield analysis, and a defensible go/conditional-go/no-go recommendation.
homepage
https://mohitagw15856.github.io/pm-claude-skills/skill/evt-dvt-pvt-gate-review.html
metadata
{"openclaw":{"emoji":"🔧"}}

EVT/DVT/PVT Gate Review Skill

Phase gates exist because hardware mistakes compound: an issue waved through EVT costs 10× at DVT and 100× in the field. This skill runs the gate the way a strong NPI lead does — score against written exit criteria, triage every open issue as blocker or waiver, read yield with its denominator, and make a recommendation someone can be held to.

What This Skill Produces

  • A scored exit-criteria checklist for the phase under review
  • An open-issue triage table (blocker / waiver / defer) with rationale
  • A yield readout by test station with failure Pareto
  • A waiver register with class, owner, expiry, and containment
  • A go / conditional-go / no-go recommendation with the conditions written down

Required Inputs

Ask for these if not provided; run the review on partial data but mark unverifiable criteria [no data — cannot score], never assumed-pass:

  • Which gate — EVT, DVT, or PVT exit (or entry to the next phase)
  • Build results — units built, units passing, failures by test station or symptom
  • Open issue list — bugs/defects with severity and status
  • Exit criteria if the program has them; otherwise use the reference set below and say so
  • Schedule pressure — the real next-build date, so the recommendation is honest about trade-offs

Gate Framework

Reference exit criteria (adapt to the program's own if provided):

Criterion EVT exit DVT exit PVT exit
Proves Design works (works-like) Design is reliable & certifiable (looks-like/works-like) Factory can build it at rate
Tooling Proto/soft tooling OK Off near-final tooling Production tooling, production line
Functional yield ≥ ~80% with failures understood ≥ ~90% ≥ ~95%, stable across line runs
Reliability Key risks tested (thermal, drop samples) Full reliability suite passed (drop, tumble, thermal cycle, HALT as applicable) ORT started; Cpk ≥ 1.33 on critical dimensions
Certs Pre-scan risks identified EMC/safety pre-scans passed Cert filings submitted/granted
Cost BOM within ~10% of target BOM within ~5%, cost-downs planned COGS at target with yield burdened in
Open issues No unresolved blockers No blockers; waivers classed & expiring Only Class C waivers, all with limit samples

Issue triage. Every open issue gets exactly one bucket: Blocker (fails a criterion, fix before gate), Waiver requested (pass the gate with the defect, under discipline below), Defer (not a gate criterion — but say why).

Waiver discipline. Class A — safety/regulatory/data-loss: never waivable. Class B — functional/reliability: waivable only with named owner, expiry date (a specific build or date at which it's fixed or the program stops), and containment for affected units. Class C — cosmetic: waivable against an approved limit sample.

Output Format

Gate review: [product] — [EVT/DVT/PVT] exit

  1. Recommendation — Go / Conditional go (conditions listed, each with owner + date) / No-go (earliest re-review)
  2. Exit criteria scorecard — criterion, target, actual, pass/fail/[no data]
  3. Yield readout — units in, units out, first-pass yield per test station, top-5 failure Pareto
  4. Open-issue triage — table: issue, severity, bucket, rationale
  5. Waiver register — waiver, class, owner, expiry, containment
  6. Risks carried forward — what the next phase inherits

Quality Checks

  • Every criterion is scored pass/fail/no-data — no blanks, no assumed passes
  • Yield is reported with denominator, build population, and per-station breakdown
  • Every waiver has a class, a named owner, an expiry, and containment
  • The recommendation names its conditions explicitly — "conditional go" without conditions is a go
  • Failure Pareto covers the top failure modes, not just an aggregate number

Anti-Patterns

  • Do not report yield without the denominator and test-station breakdown — "92% yield" on 12 hand-carried units is not data
  • Do not let a waiver pass a gate without an owner and expiry date — expiry-less waivers become the product
  • Do not waive Class A (safety/regulatory) issues under any schedule pressure
  • Do not average yield across builds with different configurations
  • Do not let "conditional go" be a euphemism for go — unconditioned conditionals are the oldest gate trick
  • Do not score a criterion pass because no data contradicts it — no data is a fail-to-verify